Christchurch Airport has formally opened the first stage of its new terminal building and started work on the second stage - including demolition of the former domestic terminal - to be completed in September 2012.
A major feature of the new terminal is a new $15 million baggage handling system, which is 750m long, Christchurch International Airport chief executive Jim Boult said.
The opening had gone without hitches, he said.
"Last week the integrated check-in hall opened, where all passengers, both international and domestic, check in," he said. This morning the first floor opened with a food court and shops.
The terminal was expected to handle six million travellers a year and to cost $237 million. So far $161.4 million has been spent on the project.
NZPA
No comments yet
Devon Funds Morning Note - 04 May 2026
MEL - Meridian joins global ranks of sustainable companies
May 5th Morning Report
ATM - a2MC recalls small volume of a2 Platinum USA label
CEN - Contact Chair to retire this year, new Chair appointed
May 1st Morning Report
GTK - Gentrack's Veovo Acquires Dubai Technology Partners
SML - Additional information following Bright Dairy announcement
April 30th Morning Report
Rua Bioscience Market Update