Christchurch Airport has formally opened the first stage of its new terminal building and started work on the second stage - including demolition of the former domestic terminal - to be completed in September 2012.
A major feature of the new terminal is a new $15 million baggage handling system, which is 750m long, Christchurch International Airport chief executive Jim Boult said.
The opening had gone without hitches, he said.
"Last week the integrated check-in hall opened, where all passengers, both international and domestic, check in," he said. This morning the first floor opened with a food court and shops.
The terminal was expected to handle six million travellers a year and to cost $237 million. So far $161.4 million has been spent on the project.
NZPA
No comments yet
May 20th Morning Report
May 19th Morning Report
PYS - PaySauce to announce F26 full year results on 27 May 2026
PEB - Draft LCD Proposes Medicare Coverage for Triage and Triage
MEL - Meridian Energy monthly operating report for April 2026
FBU - Sale of South Australian property
AIR - Air New Zealand market update
May 14th Morning Report
PEB - Pacific Edge Placement Increased to NZ$25.4 Million
Radius Care Reports Earnings Growth and 50% Higher Dividend