Wednesday 11th May 2011 |
Text too small? |
Christchurch Airport has formally opened the first stage of its new terminal building and started work on the second stage - including demolition of the former domestic terminal - to be completed in September 2012.
A major feature of the new terminal is a new $15 million baggage handling system, which is 750m long, Christchurch International Airport chief executive Jim Boult said.
The opening had gone without hitches, he said.
"Last week the integrated check-in hall opened, where all passengers, both international and domestic, check in," he said. This morning the first floor opened with a food court and shops.
The terminal was expected to handle six million travellers a year and to cost $237 million. So far $161.4 million has been spent on the project.
NZPA
No comments yet
SPG - FY26 Annual Results
PYS - PaySauce FY26 Full Year Result and Annual Report
IFT - Infratil Full Year Results for the year ended 31 March 2026
May 27th Morning Report
RYM - FY26 marks significant year of progress
FPH reports strong revenue and profit growth for FY26
IFT - Infratil Full Year Results for the year ended 31 March 2026
PEB - Advancing Medicare Coverage Goals; Cost Contained
TRU - TruScreen Completes Oversubscribed Placement
EROAD Continues Transformation, Reports FY26 Results