By Campbell McIlroy
|
Friday 31st March 2000 |
Text too small? |
UP AND AWAY: Building a level each week
|
Relatively new to Wellington with the local office only opening in May 1998, Hartner has built the 18-level apartment building in just 16 weeks.
Hartner's Wellington manager Terry Pinfold said the small site on a narrow, busy city street required a high degree of off-site manufacture, which contributed to the speedy construction.
Prefabricated steel frames were delivered to the site and erected four levels at a time. Floor slabs were then poured at two-day intervals, followed by fixing of the wall cladding panels. These panels included pre-installed windows so a full level could be completely closed in in one day, Mr Pinfold said.
The 74 studio, one, two and three-bedroom serviced apartments are expected to be completed by the end of August, three months ahead of schedule. The apartments range in size from 24sq m for the studio apartments up to 105sq m for the four penthouse apartments.
The project is being developed by Parklane Apart-
ments, which is run by Wayne Wright of Tauranga and owned by Garth Melville of Devonport, Auckland.
No comments yet
HGH - Heartland 2026 Annual General Meeting
WHS provides FY27 first quarter trading update
AIA - successfully completes new A$300 million AMTN issue
November 13th Morning Report
SPK - Response to open letter regarding FY26 financial statements
HGH - Update on proposed TSB transaction target completion date
MFT - Mainfreight Half Year Financial Results 30 September 2026
MCY - Executive leadership team changes
November 12th Morning Report
GTK - FY26 Investor Briefing Details