UP AND AWAY: Building a level each week
|
Relatively new to Wellington with the local office only opening in May 1998, Hartner has built the 18-level apartment building in just 16 weeks.
Hartner's Wellington manager Terry Pinfold said the small site on a narrow, busy city street required a high degree of off-site manufacture, which contributed to the speedy construction.
Prefabricated steel frames were delivered to the site and erected four levels at a time. Floor slabs were then poured at two-day intervals, followed by fixing of the wall cladding panels. These panels included pre-installed windows so a full level could be completely closed in in one day, Mr Pinfold said.
The 74 studio, one, two and three-bedroom serviced apartments are expected to be completed by the end of August, three months ahead of schedule. The apartments range in size from 24sq m for the studio apartments up to 105sq m for the four penthouse apartments.
The project is being developed by Parklane Apart-
ments, which is run by Wayne Wright of Tauranga and owned by Garth Melville of Devonport, Auckland.
No comments yet
EROAD Appoints New Director Progressing Board Renewal
OCA delivered record full year result
BLT - Strong revenue and underlying earnings growth
MFB - Food Bag reports full year profitability up 5.3%
TWR - Tower reports strong HY earnings
IPL - FY26 Annual Results
May 21st Morning Report
May 20th Morning Report
May 19th Morning Report
PYS - PaySauce to announce F26 full year results on 27 May 2026