Fletcher Building, New Zealand's largest building company, spent about $4 million and took almost two months to clean up and replace the roof of its Christchurch plasterboard factory that contained asbestos.
The Winstone Wallboards factory, which manufactures GIB plasterboard, was reopened on Oct. 21 following its closure on Aug. 27 after traces of asbestos were found during preparations for the roof replacement, the Auckland-based company said.
Staff were transferred to the distribution centre or to Auckland during the closure and remained on full pay, the company said. Dispatch operations at Christchurch were down for about three days, with plasterboard supplied from Fletcher's Auckland GIB plant during that time.
The new roof is expected to be completed this weekend.
Shares in Fletcher Building, the largest company on New Zealand's NZX 50 Index, slipped 0.1 percent to $9.22, and have advanced 10 percent so far this year.
BusinessDesk.co.nz
No comments yet
PYS - PaySauce to announce F26 full year results on 27 May 2026
PEB - Draft LCD Proposes Medicare Coverage for Triage and Triage
MEL - Meridian Energy monthly operating report for April 2026
FBU - Sale of South Australian property
AIR - Air New Zealand market update
May 14th Morning Report
PEB - Pacific Edge Placement Increased to NZ$25.4 Million
Radius Care Reports Earnings Growth and 50% Higher Dividend
May 13th Morning Report
Pacific Edge launches capital raise of NZ$24 million