Fletcher Building, New Zealand's largest building company, spent about $4 million and took almost two months to clean up and replace the roof of its Christchurch plasterboard factory that contained asbestos.
The Winstone Wallboards factory, which manufactures GIB plasterboard, was reopened on Oct. 21 following its closure on Aug. 27 after traces of asbestos were found during preparations for the roof replacement, the Auckland-based company said.
Staff were transferred to the distribution centre or to Auckland during the closure and remained on full pay, the company said. Dispatch operations at Christchurch were down for about three days, with plasterboard supplied from Fletcher's Auckland GIB plant during that time.
The new roof is expected to be completed this weekend.
Shares in Fletcher Building, the largest company on New Zealand's NZX 50 Index, slipped 0.1 percent to $9.22, and have advanced 10 percent so far this year.
BusinessDesk.co.nz
No comments yet
MCY - Retirement of director
AIA - April 2025 Monthly traffic update
Sanford delivers an improved half year result
May 15th Morning Report
Devon Funds Morning Note - 14 May 2025
Winton Media Release - Ayrburn Film Hub
CEN - CONTACT ENERGY APPOINTS NEW CHIEF FINANCIAL OFFICER
VCT - Vector announces strategic review for its fibre business
May 14th Morning Report
Rua approves debt facility to accelerate sales.