Genesis Energy - Huntly Unit 5 Outage Update

Monday 18th September 2023

Text too small?

Genesis has been actively pursuing options to return Huntly Unit 5 to service. Successful negotiations with third parties have resulted in an accelerated return to service which we now expect to be 31 January 2024. This timeframe is based on advice from suppliers and remains subject to any material adverse events or unforeseen logistical or supply chain related delays.

 

The financial impact of the Unit 5 outage is expected to be around $25 million net of insurance proceeds, within the $20-30 million range included in previous EBITDAF guidance. The estimate reflects the expected net impact on Genesis including the insurance deductible.

 

Any further updates on the timeline for the return to service of Huntly Unit 5 will be provided through the Transpower Planned Outage Coordination Process (POCP).

 

ENDS



  General Finance Advertising    

Comments from our readers

No comments yet

Add your comment:
Your name:
Your email:
Not displayed to the public
Comment:
Comments to Sharechat go through an approval process. Comments which are defamatory, abusive or in some way deemed inappropriate will not be approved. It is allowable to use some form of non-de-plume for your name, however we recommend real email addresses are used. Comments from free email addresses such as Gmail, Yahoo, Hotmail, etc may not be approved.

Related News:

Metro Performance Glass FY26 Market Update
Devon Funds Morning Note - 13 March 2026
Devon Funds Morning Note - 12 March 2026
TCM - Financial Model
BRM - Scheme of Arrangement Update - NZ Commerce Commission
Devon Funds Morning Note - 11 March 2026
BGP - Full Year Results to 25 January 2026
BRM - Scheme of Arrangement Update - NZ Commerce Commission
The oil shock
Air New Zealand suspends FY2026 guidance