National grid operator Transpower has advised that it will not be funding work to accelerate the Clutha-Upper Waitaki Lines Project (‘CUWLP’) transmission build in the lower South Island beyond the $10m committed by Contact and Meridian Energy in December 2019.
This means the CUWLP work programme is unlikely to be completed by the targeted commissioning date of June 2022, unless Contact and Meridian Energy contribute additional funding or the tenure of the Tiwai Point aluminium smelter is clarified.
Contact CEO Mike Fuge said the company’s commitment to helping accelerate the CUWLP work programme was unchanged, but Contact would not be making an additional financial contribution.
“We’ll continue to work with Transpower to see whether aspects of the CUWLP work programme can be optimised to mitigate delays from the recent COVID-19 restrictions. The goal is still to help move renewable electricity generation in the lower South Island north as soon as possible if the smelter closes or curtails its operations.”
About Contact Energy
Contact (contact.co.nz ) is one of New Zealand’s largest energy retailers and generators. We’re committed to a sustainable, low carbon energy future for New Zealand. We balance our commitment to lowering carbon emissions and producing renewable energy, with maintaining reliable access to energy for our customers. We generate electricity from hydro, geothermal and gas and have one of the most flexible generation portfolios in the country.
No comments yet
Comvita appoints Andrea Wilkins as Chief Marketing Officer
Synlait provides banking facilities update
CHI - Channel Infrastructure delivers solid FY25 financial result
February 27th Morning Report
TRU - Results Guidance FY2026
TRU - Results Guidance FY2026
MEE - Me Today announces six-month results to 31 December 2025
HGH - Heartland announces 1H2026 result
BRW - FY26 Half Year Results Announcement
February 25th Morning Report