National grid operator Transpower has advised that it will not be funding work to accelerate the Clutha-Upper Waitaki Lines Project (‘CUWLP’) transmission build in the lower South Island beyond the $10m committed by Contact and Meridian Energy in December 2019.
This means the CUWLP work programme is unlikely to be completed by the targeted commissioning date of June 2022, unless Contact and Meridian Energy contribute additional funding or the tenure of the Tiwai Point aluminium smelter is clarified.
Contact CEO Mike Fuge said the company’s commitment to helping accelerate the CUWLP work programme was unchanged, but Contact would not be making an additional financial contribution.
“We’ll continue to work with Transpower to see whether aspects of the CUWLP work programme can be optimised to mitigate delays from the recent COVID-19 restrictions. The goal is still to help move renewable electricity generation in the lower South Island north as soon as possible if the smelter closes or curtails its operations.”
About Contact Energy
Contact (contact.co.nz ) is one of New Zealand’s largest energy retailers and generators. We’re committed to a sustainable, low carbon energy future for New Zealand. We balance our commitment to lowering carbon emissions and producing renewable energy, with maintaining reliable access to energy for our customers. We generate electricity from hydro, geothermal and gas and have one of the most flexible generation portfolios in the country.
No comments yet
AIA - Analyst and media webcast for FY26 interim results
The Warehouse Group confirms leaner operating structure
SML - Synlait provides half year performance update
RYM - Refreshed strategy and new capital management framework
ENS - Clarification of Gina Tuzcet’s status
BGP - 4th Quarter Sales to 25 January 2026
Contact Energy 2026 Half Year Results Presentation
February 2nd Morning Report
VHP - Half year results announcement date and webcast details
Devon Funds Morning Note - 30 January 2026