By Chris Hutching
Friday 16th May 2003 |
Text too small? |
Orders for the extra turbines have been placed with the Danish manufacturer Vestas, the manufacturer of the existing turbines commissioned in 1999.
TrustPower decided to use the same make and model of turbine because of its proven suitability and to realise economies in maintenance and spare parts requirements.
About $20 million will be spent locally on siteworks and components such as lattice towers.
Resource consents are already in place and it is expected the first new turbine will be operational by mid-December, with the remainder to be commissioned and tested by May next year.
Meanwhile, Christchurch-based Windflow Technology's first wind-turbine will be erected at its Gebbies Pass on Banks Peninsula over the next few days.
The company raised $2.6 million last year for its experimental turbine that inventor Geoff Henderson said held greater promise of efficiencies than other turbines on the market.
No comments yet
SML - Synlait Milk Limited - Trading Halt of Securities
AIA - Auckland Airport announces board chair changes
AIA - Auckland Airport announces board chair changes
CEN - Tauhara commissioning progress update
FPH initiates voluntary limited recall
March 28th Morning Report
KFL Celebrates 20 Years of Excellence in Investment Mgmt.
SVR - Savor FY24 Earnings Guidance & Change in Banking Partner
NZK - NZ King Salmon Investments Limited FY24 Results
March 27th Morning Report