By Chris Hutching
Friday 16th May 2003 |
Text too small? |
Orders for the extra turbines have been placed with the Danish manufacturer Vestas, the manufacturer of the existing turbines commissioned in 1999.
TrustPower decided to use the same make and model of turbine because of its proven suitability and to realise economies in maintenance and spare parts requirements.
About $20 million will be spent locally on siteworks and components such as lattice towers.
Resource consents are already in place and it is expected the first new turbine will be operational by mid-December, with the remainder to be commissioned and tested by May next year.
Meanwhile, Christchurch-based Windflow Technology's first wind-turbine will be erected at its Gebbies Pass on Banks Peninsula over the next few days.
The company raised $2.6 million last year for its experimental turbine that inventor Geoff Henderson said held greater promise of efficiencies than other turbines on the market.
No comments yet
CMC - Appointment of Director
General Capital subsidiary General Finance update
AIA - releases long-term blueprint for the future
April 29th Morning Report
RAK - FY25 Performance and Focus; Director Retirement
PEB - Medicare LCD Effective; Pacific Edge Seeks Recoverage
MEL - New CFO and Executive Changes
PFI - Upgraded FY25 Earnings Guidance
April 28th Morning Report
Mercury appoints new Chief Sustainability Officer