By Chris Hutching
|
Friday 16th May 2003 |
Text too small? |
Orders for the extra turbines have been placed with the Danish manufacturer Vestas, the manufacturer of the existing turbines commissioned in 1999.
TrustPower decided to use the same make and model of turbine because of its proven suitability and to realise economies in maintenance and spare parts requirements.
About $20 million will be spent locally on siteworks and components such as lattice towers.
Resource consents are already in place and it is expected the first new turbine will be operational by mid-December, with the remainder to be commissioned and tested by May next year.
Meanwhile, Christchurch-based Windflow Technology's first wind-turbine will be erected at its Gebbies Pass on Banks Peninsula over the next few days.
The company raised $2.6 million last year for its experimental turbine that inventor Geoff Henderson said held greater promise of efficiencies than other turbines on the market.
No comments yet
November 19th Morning Report
STU - Steel & Tube - Trading Update and Facility Extension
ARG - Argosy FY27 Interim Result
RGI - Reefton Resource Update and PFS
NPH - 2026 Full Year Results
Devon Funds Morning Note - 18 November 2026
IFT - Interim results for the period ended 30 September 2026
November 18th Morning Report
IPL - Interim Results HY27
SEK - Seeka Announces Launch of 2026 Grower Loyalty Share Scheme