Monteith redevelopment due to start Friday

Wednesday 6th July 2011

Text too small?

The redevelopment of the Monteith's brewery in Greymouth is due to begin on Friday, with decommissioning of ageing brewing equipment.

Production of the Monteith's range would temporarily move to Mainland Brewery near Timaru, until completion of the redevelopment in March, Monteith's said today.

The project is expected to cost about $4 million.

Monteith’s Brewery manager Tony Mercer said he was working on new brews to celebrate the brewery’s re-opening in spring.

Visitor numbers at the Greymouth brewery are expected to rise to 40,000 by 2014, compared to 16,500 now.

NZPA



  General Finance Advertising    

Comments from our readers

No comments yet

Add your comment:
Your name:
Your email:
Not displayed to the public
Comment:
Comments to Sharechat go through an approval process. Comments which are defamatory, abusive or in some way deemed inappropriate will not be approved. It is allowable to use some form of non-de-plume for your name, however we recommend real email addresses are used. Comments from free email addresses such as Gmail, Yahoo, Hotmail, etc may not be approved.

Related News:

Fonterra appoints permanent COO
Manawa Energy FY24 Annual Results & Webcast Details
Seeka Provides the Results of Meeting - ASM
April 19th Morning Report
PGW Guidance Update
CNU - Commerce Commission releases draft expenditure decision
Spark announces departure of Product Director
TGG - T&G appoints new Director
April 18th Morning Report
SKC - APPOINTMENT OF CHIEF EXECUTIVE OFFICER