Meridian Energy has issued New Zealand’s Aluminium Smelter (NZAS) with a new, larger demand response notice under the NZAS Demand Response Agreement dated 30 May 2024 (DR Agreement), revoking and replacing the earlier demand response notice issued on 16 July 2024.
As a result, contract quantity under the Core Agreement between Meridian and NZAS will, depending on the start time nominated by NZAS:
• continue with a reduction of 18.75 MWh per half hour until 30 July 2024;
• reduce further progressively between 30 July 2024 and 18 August 2024 in accordance with the Demand Response Agreement; and
• reduce by 69.375 MWh per half hour from 19 August 2024 until 24 September 2024,
unless Meridian advises NZAS otherwise.
Meridian has issued the notice to help manage South Island hydro storage levels.
A copy of the demand response agreement is available on Meridian’s website.
No comments yet
TWG partners with Tata Consultancy Services
Spark announces leadership team changes
September 15h Morning Report
Tower updates FY25 guidance
September 12h Morning Report
Scott Unveils Strategy and Delivers FY25 Trading Update
September 11h Morning Report
Devon Funds Morning Note - 10 September 2025
ArborGen FY26 Guidance and Market Opportunities
BGP - Half Year Results to 27 July 2025