Meridian Energy has today issued New Zealand Aluminium Smelters Limited (NZAS) with a demand response notice under the NZAS Demand Response Agreement 2023-2024.
As a result, contract quantity under the electricity agreement between Meridian and NZAS will reduce by 25 MWh per half hour from 22 June 2024 until 20 August 2024, unless Meridian advises NZAS otherwise.
Meridian has issued the notice to help manage South Island hydro storage levels.
A copy of the demand response agreement is available on Meridian’s website.
Meridian issues demand response exercise notice to NZAS
No comments yet
January 15th Morning Report
January 14th Morning Report
WIN - Winton Announces Timing of its Interim Results for FY26
FBU - Fletcher Building Quarterly Volume Report for Q2 FY26
January 13th Morning Report
RAK - Rakon Receipt of Takeover Notice
January 12th Morning Report
GEN - Resignation of Corporate Counsel and Company Secretary
January 9th Morning Report
VSL - Confirmation of MD/CEO and Board changes