By NZPA
|
Tuesday 1st May 2007 |
Text too small? |
The Kupe project team announced today it had signed a formal agreement with Port of Marlborough to locate the project's spoolbase at Picton.
The 30cm diameter pipeline would be delivered to the spoolbase in 12m sections that would then be welded together into three individual 10km lengths.
The lengths of pipe would then be reeled into the Apache pipelaying vessel and taken to South Taranaki for laying on the seabed.
The vessel was due to arrive in Taranaki in December, with the pipelaying expected to start in early 2008, the project team said.
It was the first time a subsea gas pipeline would be laid in that way in New Zealand.
The contract for all civil works, structural components and fabrication to be undertaken at the spoolbase had been awarded to McConnell Dowell Constructors.
Meanwhile, work had finished on two 2.2km tunnels, 400m of the length onshore, to take the pipeline and an umbilical cable providing utilities to the Kupe platform under the South Taranaki coastline.
The tunnels were the longest of their type -- horizontal directional drilling (HDD) with the pipe being pushed through from onshore -- ever completed, the project team said.
The drilling was accurate, with the tunnels' subsea exit points within 6m of target.
Project director Peter Ashford said the huge effort put into the planning and execution of the tunnelling had paid off.
The estimated $980 million Kupe gas project is expected to be finished by mid-2009.
Participants are Origin Energy, the operator with a 50% shareholding, along with Genesis Energy with 31%, New Zealand Oil & Gas with 15%, and Mitsui E&P with 4%.
No comments yet
NZME 2025 Full Year Results Release Date
Turners Institutional Investor Day
February 10th Morning Report
PEB - Medicare Contractor Novitas Schedules Expert Panel
NZK Enters Into Wellboat Lease Agreement
Fonterra announces Mainland Group leadership change
OCA - Oceania announces Director changes as part of Board refresh
AIA - Analyst and media webcast for FY26 interim results
The Warehouse Group confirms leaner operating structure
SML - Synlait provides half year performance update