Christine Nikiel
|
Friday 7th November 2003 |
Text too small? |
"It's been quite difficult," he said. "Quite challenging."
Quite indeed. The $135 million convention centre, which had its roof topping ceremony last week, is second only to the building of Te Papa museum on Gray's list of difficult projects throughout his 35-year career with Fletchers.
"Some of my guys, who have been working with me [for Fletcher] for 30-odd years, say this building is one of our greatest challenges. But we knew it would be, from day one," Gray said.
The rooms were designed to seat 1500 people and required large uninterrupted spaces, meaning no columns blocking the view.
But "remarkable engineering" from Beca allowed the plan to work out, Gray said.
To enable such large, open spaces, 22-ton roof trusses support the roof and several floors below it. Huge concrete "share" walls support the weight.
About 250 Fletcher builders have worked on the project since last October. But the work is not over yet.
Fletchers still has to build a 316-room 15-level Sky City Grand Hotel for the top of the convention centre.
The $75 million hotel will be linked by two air bridges to the Sky City Casino opposite. The hotel is scheduled to open in 2005 and the convention centre in April next year.
No comments yet
SPG - FY26 Annual Results
PYS - PaySauce FY26 Full Year Result and Annual Report
IFT - Infratil Full Year Results for the year ended 31 March 2026
May 27th Morning Report
RYM - FY26 marks significant year of progress
FPH reports strong revenue and profit growth for FY26
IFT - Infratil Full Year Results for the year ended 31 March 2026
PEB - Advancing Medicare Coverage Goals; Cost Contained
TRU - TruScreen Completes Oversubscribed Placement
EROAD Continues Transformation, Reports FY26 Results