Further investigation into Genesis’ Huntly Unit 5 combined cycle gas plant outage has indicated that return to service is now expected in late May 2024, as circuit breaker components are manufactured internationally.
High hydro storage, alternative plant availability and wholesale electricity market conditions have combined to mitigate the financial impact of the outage to date. Genesis is actively pursuing options to return the unit to service earlier and has material damage and business interruption insurance cover in place.
The financial impact of this event, based on current market conditions, plant and fuel availability, and mitigating factors is estimated to be in the range of $20 million to $30 million.
Updates on the return to service of the unit will be provided through the Transpower Planned Outage Coordination Process (POCP).
ENDS
No comments yet
GTK - Gentrack's Veovo Acquires Dubai Technology Partners
SML - Additional information following Bright Dairy announcement
April 30th Morning Report
Rua Bioscience Market Update
FSF - Fonterra announces interim leadership changes
April 29th Morning Report
NZK - Blue Endeavour Pilot Farm and Wellboat Update
TRU - FY 31 March 2026 Revenue and Results Guidance Achieved
FBU - Fletcher Building sale of Fletcher Reinforcing and Wire
April 28th Morning Report