Fletcher cuts full-year earnings guidance by 15% as problematic projects get worse

Monday 20th March 2017

Text too small?

Fletcher Building has sliced about 15 percent from its annual earnings guidance after the prognosis for two major construction projects deteriorated, prompting an overhaul of the firm's bidding processes. 

The Auckland-based company expects operating earnings before interest, tax, and significant items to be between $610 million and $650 million in the year ending June 30, down from a previous estimate of $720 million to $760 million. The downgrade comes less than a month after the country's biggest building firm affirmed guidance at its first-half result, which showed the firm's construction division struggled due to problems at a major project that ran into the tens of millions of dollars. 

Fletcher Building has completed a "thorough review" of its construction division which started in late 2016 and found the major contract was likely to face bigger losses, which represents about half of the downgrade, while another major project has attracted provisions for losses due to significantly higher costs needed to complete it, and a number of smaller jobs also faced lower earnings. 

"It is very disappointing that the review of the B+I (buildings and interiors) business unit has founder weaker performance than we had previously understood," chief executive Mark Adamson said in a statement. The B+I unit accounts for about $1.5 billion of Fletcher's $2.7 billion construction book. 

Trading in Fletcher's shares was halted on Friday pending the review and has now been lifted. The stock last traded at $9.22 and has dropped 9.7 percent since reporting its first-half result on Feb. 22. 

The company refused to name the projects, citing client confidentiality, and said one of them is expected to be completed within the next few months and the other has a target date for the 2019 financial year. 

Fletcher said the main problems were in the complexity of design, subcontractor management and building programme delivery, which delayed the projects and led to higher costs. 

As a result, Fletcher has appointed a chief operating officer and a new head of risk and governance for the construction division, while a new general manager of the B+I unit will start soon. 

"We have new finance leadership and processes along with the recent implementation of a new financial management reporting system," the company said. "The criteria for bidding major construction projects have been made more stringent, and internal review processes for proposed and existing projects have been strengthened." 

 

BusinessDesk.co.nz



  General Finance Advertising    

Comments from our readers

No comments yet

Add your comment:
Your name:
Your email:
Not displayed to the public
Comment:
Comments to Sharechat go through an approval process. Comments which are defamatory, abusive or in some way deemed inappropriate will not be approved. It is allowable to use some form of non-de-plume for your name, however we recommend real email addresses are used. Comments from free email addresses such as Gmail, Yahoo, Hotmail, etc may not be approved.

Related News:

SML - Synlait Milk Limited - Trading Halt of Securities
AIA - Auckland Airport announces board chair changes
AIA - Auckland Airport announces board chair changes
CEN - Tauhara commissioning progress update
FPH initiates voluntary limited recall
March 28th Morning Report
KFL Celebrates 20 Years of Excellence in Investment Mgmt.
SVR - Savor FY24 Earnings Guidance & Change in Banking Partner
NZK - NZ King Salmon Investments Limited FY24 Results
March 27th Morning Report