Genesis Energy, the country's biggest energy retailer, will permanently retire a coal/gas fired unit at the Huntly Power Station which has been in storage as renewable and thermal generation provide more than enough electricity to meet customer demand.

The Auckland based company decided to retire the 250 megawatt Rankine unit because it wasn't needed by the wholesale market when a dry period kept hydro lake levels low. The unit has been in long term storage to be rolled out in the event of a shortage, something that hasn't eventuated.

"Supply growth over the past few years has been strong, while customer and industrial demand growth has been relatively flat," chief executive Albert Brantley said. "As a result, we have taken the decision to retire a second Rankine unit, delivering further operational efficiencies to Genesis Energy."

Genesis placed its first unit in storage in 2012, and has put more pressure on the Huntly plant to perform after previous management kept it available as a back-up to prevent winter black-outs during low rainfall.

The power company will keep two coal/gas units available at the Huntly plant and two other gas fired units.

Genesis shares were unchanged at $1.75, and have dropped 19 percent this year.

 

 

 

 

BusinessDesk.co.nz



  General Finance Advertising    

Comments from our readers

No comments yet

Add your comment:
Your name:
Your email:
Not displayed to the public
Comment:
Comments to Sharechat go through an approval process. Comments which are defamatory, abusive or in some way deemed inappropriate will not be approved. It is allowable to use some form of non-de-plume for your name, however we recommend real email addresses are used. Comments from free email addresses such as Gmail, Yahoo, Hotmail, etc may not be approved.

Related News:

AGL - Change in Senior Management
Devon Funds Morning Note - 01 May 2024
Rick Christie to step-aside as a non-executive director
CHI - New customer contract to upgrade Marsden Point
Synlait announces changes to Board of Directors
May 1st Morning Report
Devon Funds Morning Note - 30 April 2024
New Rural Advocacy Hub to be launched at Fieldays 2024
Serko signs five-year partnership renewal with Booking.com
NPH - 2024 Half Year Results Announcement Date