Fletcher Construction asks judge to dismiss CCDHB claim for leaky hospital pipes

Monday 17th October 2016

Text too small?

Capital & Coast District Health Board has no chance of winning its claims against Fletcher Construction for its work on Wellington Hospital, and the case should not go to trial, Fletcher's lawyer has told the High Court. 

Fletcher's lawyer, Kerry Fulton, has sought a summary judgment from associate judge Warwick Smith, saying CCDHB has no case. Fletcher was contracted by CCDHB to build the majority of Wellington's $346 million central hospital, a task it substantially completed in December 2008, Fulton said. The health board says there are defects in the copper pipes used in the hot and cold water system and in the system's design.

The pipes have developed pinhole leaks and the system needs to be replaced. When the health board launched the court action in May this year it said it wasn't appropriate to speculate how much a solution would cost.

The system was designed by Beca, which the district health board had its own contract with, Fulton said, while Fletcher subcontracted out the installation of the systems to specialists who have since been liquidated.  

"The design was not a responsibility resting on FCC, and it can have no liability for that," Fulton said. "CCDHB witnesses don't dispute that the defects are primarily design defects, for which FCC can't be responsible."

Fulton rejected the health board's allegations that Fletcher couldn't delegate its duty to ensure the building materials were fit for purpose.

"These pipes all came stamped compliant with the standard. What were we supposed to do? That's it. If a duty like this was said to be owed, the construction industry would come to a standstill because every contractor would think, we have to get everything audited now, and that's just plain nonsense."

The health board has also alleged the pipe manufacturer, Crane Group, breached its duty of care as it says it supplied faulty pipes, Fulton said.

"CCDHB agreed its protection post-construction against material failures was through the two-year guarantee they agreed to accept from the specialist sub-contractor. In any event, the alleged defects are not defects, and there's no prospect of that being established, and there's no prospect of establishing breach."

The hearing continues this afternoon with the health board's lawyers presenting their case.

BusinessDesk.co.nz



  General Finance Advertising    

Comments from our readers

No comments yet

Add your comment:
Your name:
Your email:
Not displayed to the public
Comment:
Comments to Sharechat go through an approval process. Comments which are defamatory, abusive or in some way deemed inappropriate will not be approved. It is allowable to use some form of non-de-plume for your name, however we recommend real email addresses are used. Comments from free email addresses such as Gmail, Yahoo, Hotmail, etc may not be approved.

Related News:

POT Financial Results for the year to 30 June 2025
MOVE FY25 Results for the year ended 30 June 2025
BPG - Completion of Retail Offer
Comvita releases results for the year ended 30 June 2025
August 29th Morning Report
Air New Zealand announces 2025 financial result
August 28th Morning Report
VSL - 2025 date of Annual Meeting of shareholders
WIN - Winton announces FY25 Annual Results
Meridian Energy Limited 2025 Full Year Financial Results