Transpower outage takes out most of Wellington for 90 minutes

Thursday 22nd April 2010

Text too small?

A fault on the national grid caused a power outage affecting 84,000 Wellington customers for approximately one and a half hours this afternoon.  

The fault occurred in the Wilton sub-station, where "vital maintenance" was being undertaken on one of the "buses" delivering a power feed to central Wellington, grid operator Transpower said.

Another bus at the substation, which was carrying load instead, failed, removing the back-up that is always supposed to be available while maintenance is occurring.

Power was restored just before 4.30pm.

 

 

 

Businesswire.co.nz



  General Finance Advertising    

Comments from our readers

No comments yet

Add your comment:
Your name:
Your email:
Not displayed to the public
Comment:
Comments to Sharechat go through an approval process. Comments which are defamatory, abusive or in some way deemed inappropriate will not be approved. It is allowable to use some form of non-de-plume for your name, however we recommend real email addresses are used. Comments from free email addresses such as Gmail, Yahoo, Hotmail, etc may not be approved.

Related News:

November 28th Morning Report
Pacific Edge Appoints Chief Commercial Officer
Ryman Healthcare reports 1H26 results
Tower reports record FY25 result, increased dividends
NZ King Salmon Investments Ltd releases FY25 (Sept) results
RBNZ - OCR lowered to 2.25%
SVR - Savor Interim Results and Trading Update
Genesis Energy Limited - Strategy & Earnings Growth On Trac
ARB - ArborGen Holdings Interim Results to 30 September 2025
FPH delivers strong growth for the first half