A fault on the national grid caused a power outage affecting 84,000 Wellington customers for approximately one and a half hours this afternoon.
The fault occurred in the Wilton sub-station, where "vital maintenance" was being undertaken on one of the "buses" delivering a power feed to central Wellington, grid operator Transpower said.
Another bus at the substation, which was carrying load instead, failed, removing the back-up that is always supposed to be available while maintenance is occurring.
Power was restored just before 4.30pm.
Businesswire.co.nz
No comments yet
NZK Market Update - Earnings Guidance Upgrade
MEL - Meridian Energy monthly operating report for March 2026
April 17th Morning Report
CCC - ESQUIRES IRELAND RECOGNISED AS THE BEST IN IRISH AWARDS
FBU - Fletcher Building Quarterly Volume Report for Q3 FY26
April 16th Morning Report
SCT - 2026 Half Year Announcement
Devon Funds Morning Note - 14 April 2026
BNP Paribas accredited as Derivatives Market Maker
GXH - Response to media report