Commissioning works at Contact’s Tauhara geothermal plant have been progressing well, with remedial work to the steam separation plant successfully completed.
Power station commissioning activities are expected to commence shortly, with first synchronisation to the system occurring in late April / early May 2024 at the earliest. After completion of power station testing activities, the 30-day reliability run required to support commercial operations could begin in late May 2024.
Contact maintains its expectation that Tauhara will be online at an initial capacity of at least 152MW in Q3 2024 and notes that a range of timing outcomes within the quarter remain possible. This reflects the potential discovery of latent commissioning issues in the next stage of power station testing, as can be expected during commissioning. Within that context, this progress announcement seeks to highlight the possibility that Tauhara could be online for winter 2024.
The project team continues to work tirelessly to accelerate the Tauhara commissioning timeline to deliver this worldclass geothermal project. Seeing Tauhara online will be a key milestone in the delivery of Contact26, Contact’s strategy to lead the decarbonisation of New Zealand.
- ends -
No comments yet
SKT - Sky ASM - Q1 Dividend Announced and Guidance Reiterated
TRA - Turners absorbs oil shock to deliver a record first half
Devon Funds Morning Note - 20 November 2026
IFT - Lodgement of Product Disclosure Statement for Capital Bond
LOD - Lodestone Energy delivers strong growth
FSF - Fonterra increases FY27 forecast Farmgate Milk Price
November 20th Morning Report
RGI - Reefton Resource Update and PFS
Devon Funds Morning Note - 19 November 2026
RYM - Ryman appoints two new directors