Transpower optimises upper North Island power delivery

Monday 8th October 2018

Text too small?

Transpower is changing the way it manages some of its most important lines in order to defer upgrades and deliver more electricity over the course of a day.

The national grid operator last week moved to two-hourly ratings on five circuits in the Bay of Plenty, the central North Island and south Auckland. This week a further three circuits in the upper North Island will move to 12 daily ratings from six previously.

The variable line ratings adjust the amount of power the lines can carry based on the expected temperature. In the middle of the night they can deliver more electricity before starting to sag; in the middle of the day they can carry less.

Transpower says the greater granularity offered by the 12 daily time periods should let it more effectively manage the critical morning and evening peak times in areas of fast-growing demand, such as South Auckland.

“VLR also helps more generation to be exported at times when it might otherwise be constrained, and avoid water being spilled at the hydro lakes.”

State-owned Transpower operates more than 12,000 kilometres of lines linking the country’s largest power stations with major consumers and local network companies. It is making more use of new technology to defer line upgrades where possible and make its processes more responsive to more variable generation from wind and solar.

Transpower started trialling VLR in 2010 on lines that are nearing maximum loads. The rest of its lines have set day-night and summer-winter ratings.

Studies done at the time indicated the change could provide about 10 percent more capacity and defer costly upgrades. The savings for South Auckland taxpayers were estimated at about $15 million. The benefit from greater access to lower-cost generation was estimated at $5 million annually.

Two of the eight circuits using VLR deliver electricity to Otahuhu. Others link Kinleith, Lichfield and Tarukenga, and Wairakei, Ohakuri and Atiamuri. The two lines between Kawerau and Trustpower’s Matahina hydro dam were added to the VLR programme last week.

Transpower says VLR is likely to become more critical as the grid becomes more dependent on wind and solar generation.

“We expect suppliers of our operating network systems will add VLR as a standard feature making its wider use more feasible.”

(BusinessDesk)



  General Finance Advertising    

Comments from our readers

No comments yet

Add your comment:
Your name:
Your email:
Not displayed to the public
Comment:
Comments to Sharechat go through an approval process. Comments which are defamatory, abusive or in some way deemed inappropriate will not be approved. It is allowable to use some form of non-de-plume for your name, however we recommend real email addresses are used. Comments from free email addresses such as Gmail, Yahoo, Hotmail, etc may not be approved.

Related News:

POT Financial Results for the year to 30 June 2025
MOVE FY25 Results for the year ended 30 June 2025
BPG - Completion of Retail Offer
Comvita releases results for the year ended 30 June 2025
August 29th Morning Report
Air New Zealand announces 2025 financial result
August 28th Morning Report
VSL - 2025 date of Annual Meeting of shareholders
WIN - Winton announces FY25 Annual Results
Meridian Energy Limited 2025 Full Year Financial Results