HALFYR: WTL: Windflow Technology Preliminary Result
16 Mar 2010 3:59 pm
WTL
16/03/2010
HALFYR
REL: 1559 HRS Windflow Technology Limited
HALFYR: WTL: Windflow Technology Preliminary Result
Windflow Technology: Interim Report 2010
Overview - Windflow's major achievements in the first half of the 09/10
financial year were:
- Installing and commissioning the remainder of Stage 3 to take Te Rere Hau
(TRH) wind farm to a total of 65 turbines.
- Delivering TRH turbines operating availability to above 93% for calendar
2009, and starting 2010 above 95% availability.
- Submitting (as part of International Electrotechnical Commission (IEC) Type
Certification) the final documents to Lloyds Register in Britain for Class 1A
Design Evaluation of the Windflow 500.
- Gaining resource consent to develop the 25 turbine Long Gully wind farm in
Wellington.
Financial Results - Windflow continued to produce a positive gross profit for
the half year. Consolidated revenue for the six months was $13.597 million
(compared with $11.834 million for the previous comparable six month period).
Direct production costs including turbine costs for the same period were
$12.694 million (compared with $10.841 million for the previous year)
resulting in a gross profit of $0.903 million for the period compared with
$0.993 million for the previous year). The result is that Windflow has
recorded a half-year loss of $1.628 million (compared with $ 1.082 million
last year).
Cash held at 31 December 2009 was $2.034 million, a reduction of $9.693
million for the six months. The reduction in cash held is attributable to an
anticipated cash outflow during the latter stages of production, the dispute
with NZ Windfarms, and some production related timing impacts. Windflow
expects to generate a cash surplus from operations over the coming period
with a corresponding improvement in its cash position.
Windflow's short-term cash situation is dependent on that of its customer NZ
Windfarms, which has released various statements about its need to raise
additional funding to complete the Te Rere Hau wind farm. If NZ Windfarms is
not successful in raising sufficient additional funding or if it were to
again withhold significant payments, then Windflow could have major cash flow
issues.
For the full year ending 30 June 2010 Windflow expects a positive gross
profit and an overall net loss similar to last year.
Windflow's financial statements have been prepared using the assumption that
Windflow is a going concern. If the going concern assumption were not
appropriate then the amounts at which items were recorded in the financial
statements could change significantly. Windflow's directors believe that the
going concern assumption is appropriate because the NZ Windfarms board has
expressed confidence in NZ Windfarms' ability to raise additional funding and
continue as a going concern.
Te Rere Hau wind farm performance - with 65 turbines operating, TRH is
establishing the reputation of the Windflow 500 as a cost-effective,
efficient, and robust design. On a site regularly experiencing severe gales
(90-120 km/h), and hurricane force winds (>120 km/h), the Windflow 500
turbines achieved availability of 93.3% - a significant accomplishment in
first year, large scale operation. For comparison the international norm for
wind farms deploying turbines from long established manufacturers is 94%
availability in the first year of operation.
Windflow and its suppliers have rectified under warranty some non-recurring
issues which arose during 2009. These issues caused overall availability in
2009 to be below 95%, triggering a warranty payment of $41,453 being payable
to NZ Windfarms.
First-year issues typically arise in the wind industry, and Windflow's
financial warranty provisions have proved adequate. The work which Windflow
carried out in 2009 has ensured that availability has stayed above 95% in
2010 to date. Warranty, operating and maintenance costs are being managed
within competitive budgets and lower than industry benchmark figures. The
lightest machine on the market for its output, the Windflow 500 is now
proving at TRH that it is one of the most reliably cost-effective.
IEC Certification - for the last four years, Windflow has worked assiduously
towards gaining the highest standard Class 1A Edition 3, IEC Type
Certification for the Windflow 500 turbine. Granted ISO 9001 certification in
June 2008, Windflow submitted final IEC calculations to Lloyds Register (LR)
in July 2009. LR has issued the Design Appraisal Document (DAD) for the
Windflow 500's blades. The DAD's for the nacelle, covering almost all major
components, and the tower are expected within weeks. These will complete the
package of three DAD's required by Lloyds Register to complete the Design
Evaluation part of IEC Type Certification.
Te Rere Hau wind farm completion - Windflow continues to manufacture the
balance of Stage 4 (the last 32 turbines for the Te Rere Hau wind farm) which
NZ Windfarms Ltd ordered in September 2008. The completion of this order has
been delayed as a result of a dispute with NZ Windfarms covering a range of
issues including project delays, funding uncertainty and concerns about
design differences between the first 49 turbines ordered for TRH and the last
48 turbines.
The concerns about the design differences have been addressed and quantified
by an independent expert report which Windflow commissioned and provided to
NZ Windfarms. Since then NZ Windfarms has ceased withholding invoices over
this matter and paid the invoices that were outstanding. In the current
calendar year, the two companies have been making good progress on
negotiating an agreement to resolve any design differences, along with the
outstanding issues about the delays to Stage 4. NZ Windfarms advised
Windflow in July 2009 that it wishes to delay Stage 4 and use the turbines at
the extension site which has higher wind speeds but which was subject to
consent. At time of writing the consent has been granted but appealed. NZ
Windfarms has reported that it is in discussion with the one appellant and
considers that it is likely agreement can be reached to have the appeal
withdrawn.
The resource consent for the Te Rere Hau extension is for 56 turbines.
Assuming it proceeds and the 32 turbines for Stage 4 of Te Rere Hau are
relocated to the extension, there will remain 56 sites, across both the
original and extension TRH sites, which are consented for the Windflow
turbine.
Long Gully Wind Farm - with cornerstone shareholder Mighty River Power (MRP),
Windflow is developing the Long Gully wind farm situated near the Wellington
suburb of Brooklyn. Resource Consent for up to 25 Windflow 500 turbines was
obtained in October. Subsequently two appeals were lodged. Windflow and MRP
are working with the appellants seeking a mediated or, if necessary,
Environment Court resolution. At the same time Windflow and MRP are
negotiating the details of a turbine sale and purchase agreement in
anticipation of the appeals being resolved.
Other Projects in the Pipeline - whilst building on its strong commitment to
work with wind farm developers and consultants nationally, Windflow continues
to explore projects and opportunities globally which might extend the scope
of the Windflow 500's reach beyond New Zealand's shores.
Production - quality is fundamental to success, and Windflow continues to
work with suppliers to ensure components of world class standard. Windflow
is also working to qualify alternative suppliers for many of the key
components in the turbine, including some which Windflow has previously
obtained from only a single supplier.
Production figures for the Financial Year 09/10 will be similar to 08/09 at
around 40 turbines, with further orders in prospect both from domestic and
international markets.
Outlook - 2009 was a year in which all businesses faced up to the global
financial crisis. The wind industry was not immune to this and growth slowed
but was still significant. Global growth was 31%, adding 37.5 GW in 2009
(the equivalent of 75,000 Windflow 500's and about $90 billion worth of
business) to bring total installations up to 158 GW. A third of these
additions were made in China, which experienced over 100% growth in 2009.
The lower than anticipated growth has led to an oversupply of wind turbines
(outside of China) and competitive price pressure from the large established
manufacturers. The NZ$ exchange rate has fluctuated significantly, at first
to the advantage of local producers, but then returning to similar levels
against the US$ and Euro as in mid-2008. Thus the net effect is still
slightly positive as regards Windflow's competitive position against European
turbines.
Encouraged by the growing track record of the Windflow 500, the Directors
remain convinced that both expanding into global markets and growing domestic
market share are eminently achievable goals.
The Directors would like to thank the Shareholders for their continuing
strong commitment to Windflow Technology. They also wish to thank Windflow's
Staff, whose talent, professionalism, expertise and creative drive have made
an important contribution to Windflow's prospects and the New Zealand
knowledge economy.
End CA:00192548 For:WTL Type:HALFYR Time:2010-03-16:15:59:11 More announcements for WTL
|
|


NZX 15 Index
| |
FREE Email News
Today's Market Numbers
| NZX 50 Index |
3346.02 |
 |
19.30 |
| S&P/ASX 200 |
4261.10 |
 |
21.80 |
| Dow Jones Industrials |
12890.50 |
 |
6.50 |
Stock Quote
Most Commented On
|