MINE: PRC: Pike River Access Roadway Through Graben Into Coal
20 Apr 2010 12:10 pm
PRC
20/04/2010
MINE
REL: 1210 HRS Pike River Coal Limited
MINE: PRC: Pike River Access Roadway Through Graben Into Coal
PIKE RIVER ACCESS ROADWAY THROUGH GRABEN INTO COAL
Pike River Coal is another step closer to the start-up of hydro-mining after
driving the first access roadway through the rock graben back into coal, says
Chief Executive Gordon Ward.
Over the past six months Pike River staff and contractors have been working
in two primary areas underground at pit-bottom, which is situated at the far
end of the access tunnel. Access roadways have been driven out towards the
hydro-mining areas west of the graben and large underground excavations are
being constructed for hydro-mining infrastructure in the southern pit-bottom
area.
"We have driven the first access roadway through the rock graben and graded
that roadway uphill back up into the coal seam. The roadway is now being
driven to the closest hydro-mining area, located 80 metres to the north-west
of the rock graben," says Mr Ward.
"The access roadways are built for the life of mine and need to be on a
constant grade to ensure that coal will wash downhill without pumping from
the uphill mining operations."
A second roadway through the graben has a further 50 metres to re-enter the
coal seam. As expected, in-seam drilling has proved to be a valuable mine
planning tool. Six in-seam holes have now been drilled into the coal seam in
a fan from the north-west down to the south, all confirming at least 300
metres of coal once through the rock graben.
All in-seam holes intersected nine metres of Brunner seam premium hard coking
coal consistent with the updated geological model. The most recent hole was
drilled through the graben and continued to the west beyond the location of
the first hydro-mining areas.
The results were consistent with the previous in-seam holes described above
and confirmed the absence of significant faulting in this target area.
Current drilling is radiating out to give detailed information for
approximately the first six months of hydro-mining extraction.
Pike River is on track to begin hydro-mining in the July-September quarter
2010, with roadways being developed within the coal seam to allow water
storage and pumping systems to be installed to support the future mining
operations.
Based on a revised production ramp-up and the latest mine plan, Pike River
has reforecast using conservative development rates of advance for roadways
and a more conservative ramp-up for hydro-mining. As a result, Pike River's
second export shipment of hard coking coal has also been pushed out to July
2010 and production for the year ended 30 June 2011 is forecast at
approximately 620,000 tonnes. The Mine is forecast to hit its average steady
state rate of approximately 1 million tonne per annum in the first half of
2011.
End CA:00193927 For:PRC Type:MINE Time:2010-04-20:12:10:55