QUARTER: PRC: Pike River Activities Report Quarter Ended 31 December 09
22 Jan 2010 1:20 pm
PRC
22/01/2010
QUARTER
REL: 1320 HRS Pike River Coal Limited
QUARTER: PRC: Pike River Activities Report Quarter Ended 31 December 09
Activities Report Quarter Ended 31 December 2009
Pike River Coal Limited (PRC)
Activities Report
Quarter ended 31 December 2009*
(*This Activities Report covers activities for the quarter ended 31 December
2009 with some updates to 21 January 2009 where relevant.)
KEY POINTS
- First Export Coal Shipment scheduled for February 2010
- Roadways Driven through Rock Graben by early February
- In-seam Drilling giving Good Results
- Hydro-Mining Production scheduled for Jul-Sep 2010 quarter
- Hard Coking Coal Spot Price at US$180 per tonne
OPERATIONS
First Export Shipment
Pike River Coal's first export shipment of 20,000 tonnes of premium hard
coking coal is due to depart Lyttelton in February 2010. One of Pike River's
Indian customers will be the recipient of this inaugural cargo which has a
value of approximately NZ$3.4 million. Pike River's second export shipment,
scheduled for the April - June 2010 quarter, will be around 40,000 tonnes.
Trucking of coal from Pike River's Coal Preparation Plant to the new rail
load out facility at Ikamatua has begun in preparation for the first export
shipment of hard coking coal.
Continuous Miner Improvements
In December 2009 Pike River announced that one of its continuous miners was
returned to the mine face after a software upgrade to the new traction
system. The upgrade was the final step in ensuring that this piece of
machinery was fully operational. The continuous miner's performance has
improved as expected for the conditions being encountered. Similar
modifications were made to the second continuous miner which is ready to
return to service as soon as a coal face is available for cutting. The
continuous miners and the roadheader are the machines that cut coal to create
mine roadways. Drill and blast operations are used where roadways need to be
constructed through rock. Once the roadways have been constructed through the
rock graben, all three machines will be in operation.
Progress Through Graben
Progress was made in 'drill and blast' construction of roadways through the
rock graben immediately ahead of pit-bottom during the December quarter.
Roadways have now been advanced through 106 metres of rock (with a total of
269 metres of roadway construction in several headings) in a faulted zone
(graben) with around 40 metres to cross before the roadway is back in coal.
The graben was encountered immediately to the west and north of pit bottom
last year by the underground in-seam drilling unit. Recent in-seam drilling
to the north shows the graben to be approximately 150 metres wide. Completion
of this part of the process by early February 2010, will allow direct access
to the main hydro-mining areas in preparation for the commencement of
hydro-mining production.
In-Seam Drilling Giving Good Results
In-seam drilling continues with the most notable result being the progress
made with in-seam drill holes from the northern pit-bottom area to the first
hydro-mining panels. As reported in the September quarterly update, one
in-seam drill hole was completed in October to the western boundary of the
graben and drilled a further 400 metres into the coal seam without
intersecting any faulting. In the December quarter, a further in-seam drill
hole was completed north of the current stone drives to intersect the western
graben boundary. The current in-seam drill hole, targeting further north into
the next hydro-mining area (to be mined 3 - 6 months after the initial
panels) has now progressed to 378 metres and is delivering good information
to update and validate the mine's geological model.
Ramp-up to Hydro-Mining
Infrastructure needed for hydro-mining continued to be developed underground
during the period. The first of the two mobile coal receiver/crushers
("Guzzler") was dispatched from Australia to the mine site in January 2010
along with the mobile roof support housing the high pressure coal cutting
monitor. Other equipment not already on-site is tracking to schedule.
First hydro-mining was forecast in the company's August 2009 announcement for
April-June 2010 quarter. Timing of first hydro-mining is dependent upon
advance rates achieved through the graben, construction of raw coal sumps in
that stone area and access roadways through coal. Commissioning of the
hydro-mining system is now scheduled for June/July 2010. The impact is to
defer approximately 120,000-150,000 tonnes of coal production to the
July-September 2010 quarter.
Work Force
Following on from the recruitment of a new Production Manager (Michael Lerch)
at the end of last year, Pike River has recently welcomed a highly
experienced Operations Manager (Doug White) to the now 11-member management
team.
Pike River has full recruitment of 150 staff required for the current stage
of operations. The final recruitment phase will begin shortly and will bring
on around 10 more staff mostly to support hydro-mining operations.
This quarter saw the completion of the initial trainee miner programme with
15 of our original 18 recruits completing their one-year training and being
promoted to full miner status.
Three medically treated injuries, none serious, occurred during the December
quarter.
Environmental
Pike River's pest and predator eradication programme, designed to create a
safe habitat for native birds, resulted in 17 stoats and 229 rats being
exterminated in the December quarter. Pike River strives to achieve industry
best practice in environmental management. No significant environmental
incidents occurred in the December quarter.
INTERNATIONAL COAL MARKET AND COAL PRICES
Pike River's first export shipment coincides with a buoyant and encouraging
international market in which world coking coal prices are expected to rise
even higher than previously forecast. International market observers
anticipate that premium hard coking coal prices could rise by 40% from April
2010 (JFY 2010) to US$180 per tonne. China is again driving demand and is
expected to import more than 20 million tonnes of hard coking coal (premium
and standard grades) in the 2010 calendar year. India, which is also heavily
reliant on high grade coking coal imports to feed its steel-manufacturing
industry, is increasingly becoming a major player in the market. India is
also projected to import more than 20 million tonnes of hard coking coal in
the 2010 calendar year, including more than six million tonnes of premium
hard coking coal. Pike River is well-placed to benefit from the current
international demand.
Note: Coal price data and China/India projections from MinAxis Pty Limited,
January 2010.
FINANCING
The Pike River Board has been addressing the alternatives available for
providing the necessary working capital and further details are due to be
released in the next few weeks.
EMISSIONS TRADING SCHEME
Parliament passed an act to revise the Emissions Trading Scheme (ETS) in
November 2009. Under this legislation, Pike River is a mandatory participant
in the ETS and will be subject to carbon costs on fugitive gas emissions from
1 July 2010. Pike River will measure actual emissions and apply for a unique
emission factor as emissions from the Pike River mine are expected to be
about one-quarter of the default levels otherwise used to calculate
liabilities.
FOR FURTHER INFORMATION PLEASE CONTACT
Gordon Ward +64 4 494 0190
Chief Executive and Managing Director
OR
Peter Whittall +64 3 769 8400
General Manager Mines
End CA:00190425 For:PRC Type:QUARTER Time:2010-01-22:13:20:46 More announcements for PRC
|
|


NZX 15 Index
| |
FREE Email News
Today's Market Numbers
| NZX 50 Index |
3350.45 |
 |
23.70 |
| S&P/ASX 200 |
4259.80 |
 |
23.10 |
| Dow Jones Industrials |
12890.50 |
 |
6.50 |
Stock Quote
Most Commented On
|