As part of meeting resource consent compliance conditions for the Te Rere Hau
wind farm, NZ Windfarms Limited ("NWF") engaged noise consultants to carry
out an extensive noise monitoring programme at Te Rere Hau during May and
August 2009. The results from this were then incorporated into a compliance
report prepared by NWF's noise consultant that was provided to Palmerston
North City Council on 21 September 2009. NWF's noise consultant concluded in
that report that the analysis indicated full compliance during the period of
the 2009 monitoring with the resource consent conditions relating to noise.
Palmerston North City Council engaged its own noise consultant to peer review
the compliance report. NWF has been provided with a copy of that report. The
review report has identified a need for further analysis of the data and
monitoring but states that "there is reasonable doubt" that Te Rere Hau is
complying with the maximum noise levels at certain locations during night
time and certain wind conditions. The report also states that further
analysis and monitoring is required to determine if there are tonal
characteristics present that may potentially merit application of a tonal
penalty to noise measurements.
NWF is working through the report to assess the implications of the
conclusions. However, NWF notes that the review report has not identified any
definitive non compliance. NWF's preliminary view is that the statements made
about possible non-compliance need further analysis.
NWF is reviewing the report with its noise consultants, including for factual
accuracy, and will seek to clarify the issues raised in the report with the
Palmerston North City Council. NWF will provide a further update when this
process has been completed.