HALFYR: NWF: NZ Windfarms Half Year Result
2 Mar 2010 9:14 am
NWF
02/03/2010
HALFYR
REL: 0914 HRS NZ Windfarms Limited
HALFYR: NWF: NZ Windfarms Half Year Result
NZ Windfarms Limited
Results for announcement to the market
Reporting Period Six months to 31 December 2009
Previous Reporting Period Six months to 31 December 2008
Amount (000s) Percentage change
Revenue from ordinary activities
1,728 (34.9)
Profit (loss) from ordinary activities after tax attributable to security
holder.
(6,535) (351.9)
Net profit (loss) attributable to security holders.
(6,535) (351.9)
Final Dividend Amount per security Imputed amount per security
Nil It is not proposed to pay a dividend
Not Applicable
Record Date Not Applicable
Dividend Payment Date Not Applicable
Comments: Refer to the attached Chairman's Review
NZ WINDFARMS LIMITED CHAIRMAN'S REVIEW
For the Six Month Period Ended 31 December 2009
The most significant event for the Company during this reporting period
occurred during November 2009 when the final Stage 3 turbines at the Te Rere
Hau wind farm were commissioned, making a total of 65 commissioned turbines.
However this achievement has been somewhat overshadowed by the dispute with
our turbine supplier, Windflow Technology Limited and the impact that it has
had on the timing of the capital raising.
FINANCIAL PERFORMANCE
Low electricity prices affected financial performance for the six months to
31 December 2009. The Loss for the period before asset impairments,
depreciation, amortisation and tax, was $1,044,000 (31 December 2008 - loss
of $1,727,000).
Electricity sales for the six months to the end of December 2009 were 40,842
MWh at an average price of $38.92/MWh.
While revenue from electricity sales has increased as turbines are
commissioned, the increase in revenue has been offset by lower interest
income as the cash funds on deposit are utilised to meet the Te Rere Hau
construction expenditure.
The net loss attributable to Equity Holders of the Parent for the six months
was $6,535,000 compared to a net profit of $2,594,000 for the six months
ended 31 December 2008. The six months to 31 December 2008 result included
$3,162,000 Discount on the acquisition of NPBB's 50% share in the Te Rere Hau
Wind Farm Joint Venture; the net deficit before the Discount on acquisition
was $568,000.
Net loss included $1,590,000 from electricity sales (31 December 2008 -
$113,000), however this was offset by lower interest income of $138,000 (31
December 2008 - $3,162,000) as available cash reserves were used to continue
construction and commissioning the Te Rere Hau wind farm.
Net assets at 31 December 2009 were $74,557,000, compared to $81,092,000 at
30 June 2009 and $82,724,000 at 31 December 2008.
During the period the Company carried out a review of the carrying values of
assets in accordance with NZ IAS 36 - Impairment of Assets, and has
determined to make an impairment charge of $6,300,000. The valuation of the
Te Rere Hau wind farm assets is very sensitive to assumptions about discount
rate and electricity price. In ascertaining the "fair value less costs to
sell" in accordance with NZ IAS 36, the Company has applied a post-tax
(nominal) discount rate of 10% consistent with the discount rate factored
into the Ministry of Economic Development's long run marginal cost modelling
on which the adopted future price path is based. Accordingly this rate
reflects the Ministry's estimate of the hurdle rate applied by a typical
investor evaluating an electricity generation project.
The wholesale electricity price path used in the discounted cash flow model
to determine fair value is based on Energy Hedge forward price contracts
through to 2012. Post 2012 the price path is based on the Ministry of
Economic Development ("MED") Energy Outlook reference scenario which was
published in September 2009.
The Company has an agreement with the Crown to receive emission units from
the Te Rere Hau project. The Company commenced earning emission reduction
units on 1 January 2008 and earned 30,390 units during the calendar year
ended 31 December 2009 (31 December 2008: 1,296 units). The emission
reduction units will be recognised as an asset at fair value at the time the
Crown issues the units and when fair value can be determined by reference to
an active market. The 2008 and 2009 units have not yet been issued by the
Crown. There is no active market for carbon credits within New Zealand at
this time. The current international market price of carbon credits typically
ranges from Euro8 to Euro12 per tonne.
TE RERE HAU PROJECT
Since 30 June 2009 the focus has been on commissioning turbines at the Te
Rere Hau wind farm and resolving the dispute with our turbine supplier,
Windflow Technology Limited. At 31 December 2009 all 28 Stage 2 turbines and
32 Stage 3 turbines have been fully commissioned, making a total of 65
turbines operational and producing electricity into the National Grid.
NZ WINDFARMS LIMITED CHAIRMAN'S REVIEW (Continued)
Windflow Technology Dispute
Your Board had always taken comfort from the fact that Windflow Technology
Limited (WTL) was committed to seeking International Electrotechnical
Commission (IEC) Class 1A Type Certification for the WF500 turbine.
Conformity with a recognised design standard assured us that the turbines
would be suitable for use at Te Rere Hau and that we could be confident in
seeking public investment in this project. As reported in August 2009, we
learned that none of the turbines would be at the standard required for IEC
Certification. At that time Windflow Technology advised that to incorporate
all the design changes in all turbines would require a fundamental refit of
those turbines and the potential cost to do this could be as high as $24
million. This meant it was essential we understood the impacts and risks of
not having these design changes.
In December 2009, we were provided with a copy of a report by a Consultant
engaged by Windflow Technology into the significance of the design
modifications. Since then NZ Windfarms has been in dialogue with Windflow
Technology over the implications of the findings from the Consultant's
report.
Resolving this matter has not been easy - it has proven difficult to sort out
and been time consuming. However the Company has made good progress on
resolving this issue with Windflow Technology and continues to work with them
to resolve outstanding issues.
Resource Consent
On 29 May 2009 NZ Windfarms lodged a resource consent application with
Tararua District Council to install 56 turbines in an area adjoining the
current consented Te Rere Hau wind farm. This Extension area has a better
wind resource than the lower slopes of the existing farm and hence NZ
Windfarms would like to preferentially locate most or all of the Batch 4
turbines in this area.
On 4 February 2010 the Company received the decision of the Joint Hearing
Commissioners in respect to the Resource Consent application for the Te Rere
Hau wind farm Eastern Extension. The Hearing Commissioners have granted
consents for the 56 additional turbines applied for. At the time of
authorising these financial statements one appeal had been lodged with the
Environment Court in respect to this decision. The Company believes the
appellant's concerns can be addressed, and has initiated discussion with the
intention of reaching an agreement to have the appeal withdrawn.
Operational performance and outlook
Some problems have been experienced with some of the turbines delivered in
the project. These problems have affected turbine availability which for the
2009 calendar year was 93.3% percent. Problems have been experienced with
cast gears on 6 turbines where an incorrect heat treatment process has made
these gears prone to cracking. All affected gears have been replaced but with
some adverse impact on availability. Five turbines have also been affected by
operating with incorrect oil filters fitted, which have potentially allowed
manufacturing debris to enter the gearboxes. These turbines are all being
inspected and parts replaced under warranty if damage is found.
A more recent problem was experienced with overheating of generator
assemblies within the turbines installed at Te Rere Hau. Windflow Technology
has completed, under warranty, a project to retrofit cooling fans to the
generator assemblies and replace generators where necessary to resolve this
issue which manifested itself when the turbines were operating for sustained
periods at high output. The Company continues to closely monitor the
effectiveness of the solution we have been provided by the manufacturer.
Availability levels should improve as these problems are resolved.
CAPITAL RAISING AND SHORT TERM FUNDING
As reported at the Company's Annual Shareholders' meeting held on 18 December
2009, following the completion of the acquisition of NPPB Pty Limited 50 per
cent share in the Te Rere Hau wind farm, your Board recognised that the
Company needed to raise additional funds to complete the Te Rere Hau project.
We assessed the options for doing this and were well advanced with plans to
go to shareholders for additional capital when Windflow Technology advised us
that none of
NZ WINDFARMS LIMITED CHAIRMAN'S REVIEW (Continued)
the turbines already supplied to the project nor any of the remaining
turbines to be supplied would comply with the design submitted by Windflow
Technology for IEC Class 1A Certification.
This information meant that the your Board had no option but to delay the
capital raising and get a third party assessment so that we understood the
impact and risks of not having these design changes incorporated into our
turbines, and whether any mitigating actions needed to be taken either with
the turbines already supplied or with those that were still to be supplied.
This is a project that is expected to have at least a 20 year life and the
life and operating cost of the turbines is fundamental to the economics of
the project.
In your Board's view, the Consultant's report has confirmed that its decision
to disclose this matter to the market and to delay the capital raising until
it obtained a clearer understanding of the implications of not receiving IEC
Certified turbines from Windflow Technology was appropriate.
As a result, the Company, after assessing alternatives, approached its
cornerstone shareholder, Vector Limited, and negotiated a short term bridging
loan facility that will provide the funds required to continue the Te Rere
Hau project and provide working capital until the capital raising is
completed. The two Vector directors on the NZ Windfarms Limited Board
immediately declared their conflict of interest in the transaction and had no
involvement in negotiations with Vector Limited or the NZ Windfarms Limited
Independent Directors' decision to enter into the loan facility.
Due to the tight deadlines in respect of the need for short term funding the
Company applied for, and was granted a waiver of NZX Listing Rule 9.2.1
seeking approval from shareholders to the entry into of the loan by way of
ordinary resolution, as the Loan constitutes a "material transaction" with a
"related party".
The Independent Directors obtained independent advice to the effect that the
terms of the Loan Facility Agreement are commercially reasonable in the
circumstances.
The last six months have been challenging but your Board remains comfortable
that the decision to delay the capital raising until the implications of not
receiving IEC certified turbines were understood, and the decision on the
resource consent application known, are in the best interest of the Company
and shareholders. Further information of the nature of the capital raising
will be released to NZX and shareholders shortly.
Despite all these issues we need to recognise that we do now have a 65
turbine, 32 megawatt wind farm operating. While not yet at warranted
availability we expect this to be achieved as the causes of downtime are
identified and rectified.
Our priority remains the completion of the Te Rere Hau project. The coming
year will focus on resolving the outstanding issues with Windflow Technology,
completing construction of Stage 4 of Te Rere Hau, and maximising the value
of the completed wind farm.
GOING CONCERN
The condensed consolidated interim financial statements have been prepared
using the going concern assumption. The continued operations of the Group are
dependent on the ability to fund future activities from operational cash
flows and funding.
The Company and its subsidiaries have prepared business plans and budgets
which indicate that cash generated as a result of operations is insufficient
for the Company to continue operating for a period of at least 12 months from
the date these financial statements were approved by the Board of Directors.
The Company is proposing to raise funding to complete the development of the
Te Rere Hau wind farm and to repay the short term loan from its cornerstone
shareholder, Vector Limited, by way of a shareholder rights issue. On
completion of the wind farm the Company's cash flow projections demonstrate
sufficient net cash surpluses to fund the ongoing operations of the wind
farm.
The Board is close to finalising the timing and method of raising funding and
further information of the nature of the rights issue will be released to NZX
and shareholders shortly.
NZ WINDFARMS LIMITED CHAIRMAN'S REVIEW (Continued)
For the reasons set out above, the Board believes the going concern
assumption is a valid basis on which to prepare the financial statements. The
Board reached this conclusion having regard to the circumstances which they
consider likely to affect the Company during the period of one year from the
date these financial statements are approved, and to circumstances which they
believe will occur after that date which could affect the validity of the
going concern assumption.
While the Board is confident in the Company's ability to continue as a going
concern, there is uncertainty with respect to achieving the operational cash
flows predicted and the raising of sufficient additional funding prior to
utilisation of available cash resources and to complete the Te Rere Hau wind
farm project. Accordingly, there is uncertainty as to whether the Company can
continue as a going concern and therefore whether it will be able to pay its
debts as and when they become due and payable. If the Company was unable to
continue in operational existence and pay debts as and when they become due
and payable, adjustments may have to be made to reflect the situation that
assets may need to be realised and liabilities extinguished other than in the
normal course of business, and at amounts which could differ significantly
from the amounts at which they are currently recorded in the statement of
financial position.
The condensed consolidated interim financial statements do not include any
adjustments relating to the recoverability and classification of recorded
asset amounts nor to the amounts and classification of liabilities that may
be necessary should the Company be unable to continue as a going concern.
The external auditor has referred to the fundamental uncertainty in its audit
report.
Derek Walker
Chairman
End CA:00191956 For:NWF Type:HALFYR Time:2010-03-02:09:14:17 More announcements for NWF
|
|


NZX 15 Index
| |
FREE Email News
Today's Market Numbers
| NZX 50 Index |
3326.74 |
 |
2.10 |
| S&P/ASX 200 |
4282.90 |
 |
7.80 |
| Dow Jones Industrials |
12884.00 |
 |
5.80 |
Stock Quote
Most Commented On
|