GENERAL: CEN: Contact completes Tauhara One ahead of schedule
25 May 2010 8:44 am
CEN
25/05/2010
GENERAL
REL: 0844 HRS Contact Energy Limited
GENERAL: CEN: Contact completes Tauhara One ahead of schedule
25 May 2010
CONTACT COMPLETES TAUHARA ONE AHEAD OF SCHEDULE
Contact Energy has completed its new $100 million, 23 megawatt geothermal
power station near Taupo, three weeks ahead of schedule.
"The Te Huka binary plant - also known as Tauhara One - has been completed
ahead of schedule and under budget," Contact's Managing Director David
Baldwin said.
The power station will provide enough baseload renewable energy to power
approximately 23,000 homes.
Tauhara One is the first project in Contact's $600 million current investment
programme to be completed. This year Contact will also open the 200 megawatt,
$250 million Stratford gas-fired fast-start peakers and the $250 million
Ahuroa gas storage facility in Taranaki - projects which will add operational
flexibility to Contact's portfolio and additional peaking capacity to New
Zealand.
Mr Baldwin said construction of the new peaking power station at Stratford
was also progressing well, with construction of the station due to be
completed by the end of May at which point it will begin commissioning. All
testing of the plant is due to be completed by October.
In addition the first phase of the Ahuroa Gas Storage project, which rounds
out Contact's current investment programme, is on track to be complete by the
end of 2010.
Mr Baldwin said the early delivery of Tauhara One was an important milestone
in Contact's geothermal growth strategy. Contact is currently seeking
consents for its 250 MW Tauhara Two geothermal power station through a Board
of Inquiry process and advancing development of its consented 220 MW Te Mihi
power station.
The company also expects exploration of the Taheke geothermal resource to
commence shortly, in conjunction with its joint venture partner, the Taheke
8C Incorporation.